ENGINEERS BREAK SILENCE ON PROBLEMS AT MUSKRAT FALLS

For most engineers the
execution of a megaproject is principally about the calibre of those in charge
of management. Many don’t concern themselves with issues like water management, the question of whether it is a ‘political’ project, or whether the government has made a
premature sanction decision. Most simply want the construction phase to benefit
from the best practices of the industry and their profession.



The Muskrat Falls project is proceeding poorly; even the Nalcor CEO has been forced to admit he can’t
guarantee either the schedule or the budget will be achieved.



Imagine, therefore, that you
had a group of professionals weigh in on how they would “fix” the problem of “slippage”
and address fundamental cost and other issues.  What
do you think they might they say?



Recently, I had that
opportunity; some engineers are at their wits end over how the project is managed. It was not just a theoretical exercise; they are intimately familiar with the Muskrat Falls project. 




While Nalcor is not likely
to listen, I thought the public should have a better understanding of the type
and magnitude of the problems experienced at Muskrat Falls, and why the future of
the project is in doubt.



These are the top four
recommendations of those engineers:



1.    
Remove
several managers in the project management system. The project simply needs
better managers; this has been a problem from the very beginning.

2.    
Relocate
all of the project team staying in St. John’s to Happy Valley- Goose Bay. SHUT DOWN
the Torbay office, except for possibly a few accounting people. Relocate all
key management and engineering staff to the MF site; the very idea of managing
such a project remotely from St. John’s is expensive and damaging to morale. Even
minor decisions have to be referred to St. John’s. The construction site has
suffered from low morale from the start. Besides, major projects are not
normally managed in such a way.

3.    
Descope,
that is to say reduce the scope of the Astaldi contract by removing the
powerhouse and some of the civil work from the contractor. One engineer suggested
replacing Astaldi, that it might be cheaper if Nalcor simply bought out the
Astaldi contract.  Another engineer
suggested Astaldi ought to have been partnered with a contractor with the
strengths it lacked.



(Astaldi
was given the contract only because its bid price was lowest; even then it was
not a lump-sum bid. Astaldi is said to have no cold weather experience and no
union based experience. Weak Astaldi management has been “beefed up” with weak
Nalcor management. Recently, an ex-Kiewit manager replaced the one at Astaldi. Some
productivity improvements have been reported.)

4.    
Make
the Muskrat Falls site an “open site” and walk away from the current labour
language in the union agreement. For readers not familiar, an “open site” is variously
defined as a labour force model in which all unions are permitted to have
employees (i.e. not a “closed shop”) working together. Another model is one in
which both union and non-union workers are permitted to be employed on a work
site.  Both models are based upon
securing the best labour force available, and where everyone is paid well. The
“Teamsters” or “closed-shop” model, used at the Vale project, in Long Harbour, was
reported to be highly unproductive . That is the model adopted for the Muskrat
Falls project, too.


Other Recommendations:

  1. Establish a project
    execution plan.  There has never
    been a project execution plan for this project. Such a plan tends to be what
    one engineer called a “wordy” document but it is a critical piece of work
    because it outlines a construction strategy, describes how milestones will
    be achieved, and identifies the risks and how to manage them. (An
    execution strategy also identifies the planning tools and strategies to
    assure productivity and break down work packages; it reflects the
    challenges and takes into account the size and complexity of such a large
    project. It helps define solutions to labour productivity issues, project
    management, workface planning and organization, always using industry
    based best practices. Weather, snow, and cold temperatures would have been
    a major focus of such an execution strategy.)
6.    
Establish
a meaningful updated schedule based upon actual measured completeness and what
remains to be done. The engineers state that if a recent (two months ago) audit
had been undertaken of powerhouse/spillway contract the completion figure might be closer to 9% than to the 26.3%
reported by the government’s oversight committee at the end of March, 2015.



Of
course, the oversight committee was only parroting a Nalcor figure (35% was the
“planned” scheduled progress figure to March 2015
). 9% is a long way from 35%! The oversight committee also reported
that 37.5% of the budget for the Generation Facility was incurred at the
end of December, 2014.



As
the engineers point out, the devil is in the details. They state the public
will never know the truth about “real” progress at Muskrat unless an independent
3
rd party conducts a quantity survey based on known construction
measures.



The
engineers state they have never witnessed “change-orders” appear so fast as at
Muskrat Falls. Such change orders are a major reason for cost overruns.  (The engineers also raised the point that if
you don’t tie administration hours to project progress, you can burn a lot of
money and show no actual site completion.)



One
person interviewed stated that Nalcor has what he termed a “self-controlled”
budget. There is no independent budget manager. 
He stated he has never seen financials controls like on this project where
monies are advanced without any consideration for the amount actually allocated
for a piece of work.    


7.    
Investigate
thoroughly the “self-performing” approach taken to quality control on site
contracts. Rather than Nalcor having established an independent third party
inspection and testing process of supplied equipment and materials, the
contracts are written so that the Quality Assurance is performed by the
contractor.



One
example given was with respect to MTR Certificate for rebar (This is a Mill
Test Report, a quality assurance document). Nalcor was asked if any testing had
been conducted on the material. The reply: “that’s Astaldi’s responsibility”.  The engineers stated this just does not happen
on major construction projects. This is the Owner’s role; it is further proof,
they say, Nalcor is not qualified to be running the Muskrat Falls project.  

8.    
Review
major contracts in regards to their ability to control total cost.



One
engineer stated that Nalcor needs an independent group to audit both the work
performed and the contracts it has awarded; otherwise, the door is wide open to
cost overruns.



He
stated that while Nalcor says its contracts are “unit price” based, Astaldi, for
example, can perform work in a most inefficient way and still invoice Nalcor.


9.    
Investigate
in detail the costing for the project and existing unorthodox (to say the
least) project controls methodology. These are not this Blogger’s words! The
engineer stated he has never seen more creative accounting with money moved
around from one account to another; presumably, he stated, the money will eventually
run out.

10.  Review the use of “first of a
kind” or what is normally considered proto-types in the case of the
turbine governors and possibly other components. Though the Chinese company had
manufactured smaller turbines, it has not built any as large as those produced
for Muskrat Falls. Yet, Nalcor did not provide oversight, for quality assurance
purposes, when those turbines were built.


Any experienced project manager reading those recommendations
will be surprised just how sweeping are that group’s proposals for change on
the Muskrat Falls construction site.
One would have to conclude the management problems are
endemic to an extent that the project is doomed to suffer a very late completion,
major cost overruns, and a poor quality of work, too, due to the absence of an
adequate Quality Assurance program.


The engineers state that Nalcor’s decision to “self-manage”
the project was its first and worst decision. The Nalcor management team, except
for a couple of individuals, are simply not of a calibre to be undertaking such
a large project, they said.


I would only add these engineers have no malicious intent;
the contrary is true. They see a megaproject very poorly managed and they don’t want it to fail.

Finally, a question for the oversight committee:how can so many critically important issues go unnoticed as you put claim to an oversight role?  

It is time for them, Nalcor, and the government to stop pretending everything is fine. 
Des Sullivan
Des Sullivan
St. John's, Newfoundland and Labrador, Canada Uncle Gnarley is hosted by Des Sullivan, of St. John's. He is a businessman engaged over three decades in real estate management and development companies and in retail. He is currently a Director of Dorset Investments Limited and Donovan Holdings Limited. During his early career he served as Executive Assistant to Premier's Frank D. Moores (1975-1979) and Brian Peckford (1979-1985). He also served as a Part-Time Board Member on the Canada-Newfoundland Labrador Offshore Petroleum Board (C-NLOPB). Uncle Gnarley appears on the masthead representing serious and unambiguous positions on NL politics and public policy. Uncle Gnarley is a fiscal conservative possessing distinctly liberal values and a non-partisan persusasion. Those values and opinions underlie this writer's views on NL's politics, economy and society. Uncle Gnarley publishes Monday mornings and more often when events warrant.

REMEMBERING BILL MARSHALL

Bill left public life shortly after the signing of the Atlantic Accord and became a member of the Court of Appeal until his retirement in 2003. During his time on the court he was involved in a number of successful appeals which overturned wrongful convictions, for which he was recognized by Innocence Canada. Bill had a special place in his heart for the underdog.

Churchill Falls Explainer (Coles Notes version)

If CFLCo is required to maximize its profit, then CFLCo should sell its electricity to the highest bidder(s) on the most advantageous terms available.

END OF THE UPPER CHURCHILL POWER CONTRACT: IMPROVING OUR BARGAINING POWER

This is the most important set of negotiations we have engaged in since the Atlantic Accord and Hibernia. Despite being a small jurisdiction we proved to be smart and nimble enough to negotiate good deals on both. They have stood the test of time and have resulted in billions of dollars in royalties and created an industry which represents over a quarter of our economy. Will we prove to be smart and nimble enough to do the same with the Upper Churchill?

3 COMMENTS

  1. Some of this is the normal type of noise you hear on a project. Some of it though is likely very well based.

    But perhaps the most interesting comment is No. 9. When you look at the oversight report and see the consumed budget, and compare it to the physical progress on site something just does not add up. The project is running late, yet there has been no official change to the project budget?

    I suspect they don't want to release this information until after the election. But the election is the very reason why the public need to know!

    Nalcor should be completing quarterly (if not monthly) forecasts of the project schedule and cost. This should include all known, and predicted changes to the contract. For example if Nalcor have prices for the North and South dams, which exceed the allocated budget, then the monthly forecast should be revised even though the contract is not strictly awarded yet. Likewise the forecast needs to be updated to account for Change Order costs. Even though the Change Orders are in dispute, the forecast in the monthly cost report needs to account for them (at least partially). Not revising the forecast, due to paperwork and process, is against IFRS provisions.

    Ed Martin and Gilbert Bennett need to come clean on the realities surrounding the cost and schedule on this project. The way progress is going I would not expect power until 2019 as a best case scenario. Nalcor keep talking about recovery plans, but the progress numbers are not recovering.

  2. Good day to Uncle Gnarley, and many thanks to you and your comrades for having the courage and smarts, (and for putting in the work and expense), to “call it like it is” on behalf of future generations.
    2 questions:
    1. When are we (the general public) going to stop pretending that we actually live in a democracy, while the “elected”, (I.E. professional suck-ups (mostly) who are really appointed through a corrupt and archaic political system), do as they damn well please despite all reason, logic and public demands?

    2. What is Organized Crime? (Police definition follows), and does it accurately describe what really happens in Government/caucus?

    Canadian Definition: Within Canadian law enforcement, a legal definition for organized crime has only existed since the late 1990's following the enactment of Bill C-95. Amendments to this area of the Criminal Code have led to the present legal definition found within section 467.1(1) of the Criminal Code of Canada , which states a "criminal organization" means a group, however organized, that:
    (a) is composed of three or more persons in or outside Canada; and,
    (b) has as one of its main purposes or main activities the facilitation or commission of one or more serious offences, that, if committed, would likely result in the direct or indirect receipt of a material benefit, including a financial benefit, by the group or by any one of the persons who constitute the group.
    Source: http://www.rcmp-grc.gc.ca/soc-cgco/what-quoi-eng.htm

    Muskrat Falls is a (very) serious offense. It is being committed as we speak. Many, including appointed officials are receiving financial benefits, (each pay period). Materials benefits include publicly funded pensions. Who knows what else? They won’t escape history, and they can’t escape their souls either.

  3. Look what went on in the Montreal area regarding public money, construction projects, engineering firms, and construction compnies. From the beginning this project has not passed the smell test and it is smelling worse with each passing month. Why the rush and why the secrecy? Why SNC Lavalin? Far too many questions regarding the fundamental nature of this project. The ratepayers of this province will be paying for the project long after the well paid principals have moved on. As a public project the public deserve to have these questions answered.

    John D Pippy