SECOND FORENSIC AUDIT REPORT: EVIDENCE OF MALFEASANCE?

EVIDENCE OF MALFEASANCE?: A REVIEW OF THE FORENSIC
AUDIT REPORT INTO THE MUSKRAT FALLS PROJECT (PHASE II)


The second Forensic Audit Report prepared by the accounting
firm of Grant Thornton has now been released to the public. It will constitute
the major focus of Phase II, the “Construction Phase”, of the Commission of
Inquiry into the Muskrat Falls Project (MFP).

This Report builds on the main conclusions of the first one released
in September 2018, prior to the beginning of public hearings presided over by
Judge Richard LeBlanc. It concluded that, at the time of sanction, a
“combination of…potential misstatements may have resulted in the Interconnected
Island Option (the Muskrat Falls project) no longer being considered the least
cost option at the time of sanctioning.” In other words, had the Cumulative
Present Worth (CPW) – the present value methodology used to compare the
Isolated Island and the Interconnected Island options – been  objectively assessed, the Muskrat Falls
Project was probably not then, or ever, “least-cost”.


What had GT uncovered in order to come to that conclusion?

The Forensic Auditor found that Nalcor had underfunded the
contingency allocated for Tactical Risk exposure, provided no contingency
funding for Strategic Risk and pursued Sanction knowing that the project
Schedule had, at most, a 3% probability of being met.

Those findings and observations were repeatedly confirmed in
testimony given by multiple Witnesses at the Inquiry, including from Nalcor’s
key Consultants. 

Inquiry Commissioner, Judge Richard LeBlanc

The current Report
reviews the actual contract Bids for the two largest Work Packages and compares
them with the allocations contained in the Base Estimate. It also compares the
actual costs for the Work Packages against those incurred during the Construction
Phase; that is from December 18, 2012 to March 31, 2018.


 The “Base Estimate”,
prepared by SNC-Lavalin personnel, under the direction of Nalcor’s Deputy
Project Director, is said to have constituted 70% of the total project Estimate.
The other 30% was calculated solely by Nalcor. Together, the figures comprise
the DG3 numbers used to sanction the project. 


At the outset, we would suggest that the revelations of the
Forensic Auditor constitute a serious indictment of the honesty and integrity
of Nalcor, as a publicly-owned Crown Corporation. The evidence confirms that
until Stan Marshall became CEO of Nalcor and offered up a forecast final cost
that was based upon the project’s escalating cost history, the public was
largely kept in the dark. 


It is worth reminding readers that former Premier Dunderdale acknowledged
during her testimony in December that she was made aware by former CEO Ed
Martin, prior to sanction, that a $500 million overrun was possible. The GT
Report confirms that that figure – the threat of which ought to have been a
showstopper – was overtaken within just four
months
after Sanction. The excerpt (below) from GT Report (p. 13) provides
this confirmation.
 


(CH0007 refers to the Astaldi contract for the intake,
powerhouse, spillway and transition dams. CT0327-001, referenced later, is the
Vallard combined work package for the Transmission Line (known as the Labrador
Island Link, LIL, which does not include the line between Muskrat Falls and
Churchill Falls, known as Labrador Transmission Assets, LTA, and for which the
contract was also awarded to Valard!)


“Nalcor was aware that their original schedule was
aggressive”, says GT, based upon a DG3 Cost and Schedule Risk Analysis Report,
dated October 2012. The Dunderdale Government gave Nalcor Project sanction in
December 2012. With almost no hope of being met under any circumstances, the
Construction Schedule was compressed because “Financial Close” had not been
achieved. 


The “Financial Close” provision required that the Province
meet all the conditions of the “Term Sheet” for the Federal Loan Guarantee (FLG)
before Nalcor could access the billions of dollars required to finance the major
contracts and proceed with the project. In particular the Utilities and Review
Board of Nova Scotia had to give its approval for it to become a “regional”
project deserving support from the national government!


At the time of Sanction, the Feds and the Province were still
negotiating the Federal Loan Guarantee. In addition, Release of the Labrador
Island Link Transmission Line (LIL) Environmental Assessment, expected in April
2013 (which, strange as it may sound, was separate from the work of the Lower
Churchill Environmental Panel), did not actually occur until November 26 – a
delay of six months. Effectively, GT reports, the date for first power was
shifted from June to December, 2017 and the date for full power six months
later.


The mention of the date of delay in “Financial Close” is
important for two other reasons. Firstly, it delayed the award of the Astaldi
contract to just ahead of Winter 2012/13 which was disastrous for a company that,
arguably, should not have been awarded the contract in the first place. 


GT quotes Don Delarosbil, Astaldi Project Manager, offering
this explanation: “if you start in
November instead of June you’re not just losing four months, you’re probably
losing ten months. You almost lost a year of construction”.
(P.12) 


The second reason that the date of “Financial Close” is
important is that the delay afforded Nalcor, then in possession of several
large bids for work packages, created absolute certainty that its “Base
Estimate” was far too low!


In effect, Nalcor was given a timely opportunity to cancel the
project. GT states: “Nalcor had the ability to stop construction without
funding the remaining cost to complete. However, once the FLG was executed
Nalcor/GNL were committed to funding the project” including the cost overruns. The
likelihood of such a cancellation, however, diminishes with evidence contained
in the Forensic Audit that Nalcor had committed approximately $900 million to
the project prior to the date of Financial Close. (p.10) Nalcor had adopted the
flawed concept of sunk cost which meant that they believed the project must not
be stopped once such a major commitment had been made. This led them to ignore
all the red lights which should have compelled them to seek an “off ramp” to
terminate the project!


The Inquiry is not just about the decisions of Nalcor; it is
about those taken by the Government. A key question is whether the Crown
Corporation had fully informed the Dunderdale Government, prior to Financial
Close, that bid prices had exceeded budgeted amounts and that an underfunded contingency
allocation had already run out and that overruns of 25% had already been
recorded? Following on that question is another: if the Government was
informed, did they initiate appropriate reviews to better define the risk to
the province and assess if the project should be shut down, in consequence of
that risk?


Not surprisingly, the GT Report offers mounting evidence that
the Government of Canada knew or ought to have known that the Muskrat Falls
project was a financial travesty that would economically endanger the province.
Rightfully, the IE will be examined during this phase of the Inquiry at which
time he will be asked to address what he knew and the role he played in
informing the Government of Canada. As a start, we will need to know if and when
he informed the Federal Government not just of Nalcor’s financially flawed
project but also regarding the impossible schedule – one that had seriously
slipped by the time of financial close. 


Phase I of the Inquiry had confirmed that Nalcor knew, having
been made aware both by its Consultants and the IE, of a plethora of project risks.
The IE warned Nalcor, for example, “that the contingency they selected for the
LCP (less than 7%) was less than the low end of the range of what the IE
typically sees at comparable DG3 stage gates.” (P.16)


Apart from Nalcor, if the Federal Government was also
informed, did they just turn a blind eye to the potential consequences for the
Province, the latter having signed a completion guarantee? It was the
completion guarantee that placed the financial obligation to complete the
project on the back of the province!


That issue notwithstanding, there is still Nalcor’s “dam the
torpedoes” approach to obtaining Project Sanction. The Forensic Auditor states
that “Nothing came to our attention to indicate that Nalcor attempted to
recalculate the contingency and/or the entire capital cost estimate between
April 2013 and financial close (November 2013).” Underlining the point, GT
notes that “At the time of financial close, the project schedule was delayed by
six months, demonstrating that the 97% chance of schedule slippage determined
at sanctioning was in fact materializing.” (P.17)


One other thing is clear: while Nalcor’s Project Management
Team (PMT) monitored the forecast growth in cost to complete the project, on at
least one occasion – March 2014 – GT observed that Nalcor did not include in
the estimate “forecasted costs due to Alstaldi’s performance and delays”. GT
stated that this failure was contrary to best practices. GT also noted “there were
instances where the Nalcor Executives knew that the cost for the project
increased months before the budget increase was approved by the board of
directors…”

While V-P Gilbert Bennett and CEO Ed Martin were kept informed,
we also know that they never shared up-to-date information with the public.   

During this Audit, GT reviewed six work packages (see Exhibit
below) having “variances which exceeded $100 million”. The review covered the
reporting period which ran from the original sanction budget ($6.2 billion) to March
2018 when the forecast final cost was $10.1 billion plus financing costs. The
reader will note that the final details of three of the six work packages have
been redacted for reasons of “commercial sensitivity”, the contracts still
on-going. Our summary and comment will, therefore, be limited to the three contracts
fully considered by GT. Taken together, the three – CH0007-Astaldi, CT0327, and
Engineering, Procurement, Contracting and Management (EPCM) -represent 61% of
the total cost overruns of $3.915 billion.  All six contracts are listed in the Exhibit below.




Astaldi

The Astaldi Contract (CH007) was the largest tendered Work
Package on the project. GT notes that as of March 2018, at which time the
project was suffering overruns of $3.9 billion, Astaldi accounted for 31% of the
overruns or $1.2 billion.


The Astaldi Contract will come under severe scrutiny in the
coming weeks not least due to its unsuitability to do the work. The question
that has always needed clarity is this: who made the decision to award them the
contract and why? 


Nalcor disregarded two higher bids from Canadian companies –
the only two having project knowledge of construction in Labrador’s sub-Arctic
conditions.  


Of the nine companies that answered the prequalification
invitation, four of them were selected to participate in a Request For
Proposals (“RFP”). The two Canadian companies were AeconJV, IKC and two foreign
companies: Astaldi and Salini JV.   The Bids were received on April 16, 2013. The
Exhibit below shows the Bid prices received and, importantly, the number of
labour hours contained in each Bid price.


Outside of the failure to include adequate contingency
allowances, the project was challenged by an impossible project schedule, an
unqualified Nalcor senior executive and an inexperienced project management
team. The selection of Astaldi only magnified those deficiencies. The
Commission of Inquiry will need to be focussed on them because key management
issues often get lost in a barrage of rhetoric from self-serving Witnesses. This
is the same stuff that just a few years ago helped acclaim those executives as
“international experts”.  


The Astaldi debacle is multi-faceted and is best understood only
if certain key questions are addressed to the Company and to the Forensic
Auditor. They include: what factors were assessed in the pre-qualification
process other than the Bid price and what weights were assigned? What weight
was given to construction experience in northern climates, to previous
experience in building hydro-electric projects globally, and to working with
indigenous people? What references were sought from other clients of Astaldi?
What weight was assigned to depth of their financial resources?


GT’s analysis of the Bids, not surprisingly, deals almost
completely with the number of labour hours included in each Bid (line 2 of the
above Exhibit) in order to complete the work. This is the “productivity” issue
around which hangs the issue of cost overruns and questions related to “low-balling”
of the Estimates. Those assertions were made by the gentleman known as the
“Anonymous Engineer” who had worked in this area of the project.



GT observed that “The total labour hours included in the four
bids ranged from 5.85 million to 9.51 million, an increase ranging from 60% to
160% over the DG3 estimate.” (P.28) 
Nalcor’s DG3 estimate “included 3.66 million labour hours” in contrast
to 6.83 million hours included in the Astaldi Bid – a difference of 3.17
million hours (see Exhibit below).




Not surprisingly, the fiction of the DG3 Estimate now begins
to attain focus, except that it gets worse. 


Over the years many have expressed exasperation that a company
as inexperienced in sub-Arctic conditions as Astaldi could be selected to carry
out a megaproject in the wilds of Labrador. When a more experienced Owner would
have disqualified the contractor at the pre-qualification stage fearing the
obvious, Nalcor’s scoring system for contractor selection favored the lowest
bidder. Stated GT, “regardless of lower scores in execution of the work”….both Salini
and Astaldi “were selected for further consideration.” (p. 28)


Unfortunately, the Report exhibits large gaps of analysis including,
among others, an assessment of the contract language that wedded Nalcor to Astaldi
and the opportunities it afforded for extra billing. We are left to assume that
the mistake of selecting Astaldi could not be remedied, a swift firing having
been perceived as too expensive. However the failure to act on a timely basis
in removing Astaldi from the job was an egregious lapse on the part of the new
CEO and his management team, which they acknowledged when in November of 2018
they reached the inevitable conclusion that Astaldi must be replaced!


It also appears that the contract contained both “lump sum”
and “unit priced” components, the latter exposed to interpretation and inflation.
Who cannot remember CEO Ed Martin’s varied characterization of the contract as
a lump sum contract with incentives for performance, leaving one to wonder what
Astaldi and the public purse had actually bargained for?


That said, GT confirms that “once Astaldi was chosen…and work commenced,
costs grew significantly. The overrun, as of March 2018, was attributable to
the bridge agreement and completion agreement, change orders and unallocated
scope.” (p. 29) GT states: “The Astaldi contract was signed on November 29, 2013
(the date of financial close) for $1.024 billion (excluding an adjustment of
$64 million). After taking nearly a year to ramp up for the work, by mid-2015
Astaldi was soon in deep financial trouble.

Nalcor was now faced with saving a poor performing Company. 

Grant Thornton confirms that Astaldi had completed a “less
than expected production rate of concrete placement and being behind schedule…”
An internal analysis conducted by Nalcor in mid-2015 “concluded, that based on
the amount of funds spent on labour during 2014 there was a significant cost
gap and that it could range from $500 million to over $800 million to complete
the scope of work.”(p.30)


What followed were a series of agreements with Astaldi in an
effort to keep it solvent including a ‘supplemental’ agreement and a ‘bridging’
agreement. GT does not inform us if Cabinet approval was sought on those
agreements or if Government’s agreement to underwrite any requests from Nalcor
for contingent equity sufficed. The GT Report notes that cash advances were made
to Astaldi but we are not told why or if the Government was informed and
approved of them. These unusual cash advances had been pointed out by a
“naysayer” at Nalcor’s AGM!


As noted already, the issue of productivity is prominent in the
Report, in relation to Astaldi and hence, to the problem of cost escalation. Astaldi’s
scope of work required that it pour approximately 478,000 cubic meters of
concrete. Astaldi had assumed a conservative 6.57 direct labour hours for each
meter of concrete poured, in contrast to Nalcor’s 4.50 labour hours (see
Exhibit below). However, even the Astaldi estimate did not come close to the
actual direct labour hours required per meter of concrete.  According to the Forensic Audit the number
never went below 14 “direct” labour hours per cubic meter of concrete. The
Indirect labour hours have a wide variance with Nalcor’s DG3 estimates, too,
making Nalcor’s claim to a sound “Base Estimate” arrant nonsense.

GT adds another statistical note which, alone, magnifies the
futility of the goal the Company thought it might achieve. Says GT, in order to
meet the schedule, “Astaldi on average would have had to place approximately
13,300 m3 per month (478,000 m3/36 months) cubic meters of concrete each month,
including the winter months. This production level was attained nine times out
of 57 months since commencement of the project in November 2013 (through August
2018).”


A Study conducted in 2015 by the Ibbs Consulting Group, Inc. for
Astaldi and Nalcor on the problem of productivity reported that “Labor productivity
is degraded on Muskrat Falls by too much waiting time, too much rework, and not
enough overall site coordination.”


It is noteworthy that while the Astaldi contract allowed for 1
million more “direct” labour hours than did the Nalcor estimate at sanction, Nalcor had
allowed in its Base Estimate the cost of an Integrated Cover System
(“ICS”), AKA the “Dome”. According to GT, the ICS was supposed to
“allow the workers to work comfortably inside the structure during the winter
season resulting in no loss of labour productivity due to the climate.”


The “Dome” was demolished even before it was completed. As to
whether it made any sense from an engineering perspective, GT’s Consultant
makes this observation (p. 39):


 “Not common and warranted detailed scrutiny”. Did the idea of
the “Dome” originate with Astaldi? Did Nalcor buy into the idea without first
assessing its merits? 


GT cites the Williams Engineering Report (page 38) stating
that Astaldi was the only bidder who planned to work through the winter. The
obvious question: was this poorly understood and expensive idea a major factor
in the selection of Astaldi as the preferred bidder? While an uninformed public
will certainly want to know who paid for the $100 million plus debacle, they
also have a right to know, the “Dome” having failed, whether Nalcor pushed Astaldi
to work through the winter at enormous expense and the knowledge that
productivity was negligible.

Fearing “Astaldi’s (poor) financial strength, i.e. their
ability to absorb losses of such magnitude” Nalcor soon found itself required
to consider paying Astaldi “additional compensation in the amount of $743
million”. Exhibiting its own lack of management depth, Nalcor sought out the
assistance of Westney Consulting to perform “an analysis to determine the best
course of action.” Westney essentially concluded that paying Astaldi
represented a better alternative than replacing Astaldi. And so (costly)
negotiations soon got underway to help keep Astaldi afloat.


Nalcor entered into a “bridge agreement” initially with
Astaldi as negotiations continued over the whole amount claimed. It is
important to note that “effective as of December 1, 2016….The total contract
price was $1.83 billion…inclusive of the scope of the original contract and all
change orders up to and including November 30, 2016. “…another $78 million
for additional travel and escalation related to the completion contract”, was
also added. The “settlement”, states GT, “of $884 ($806 million+$78 million)
resulted in a total package budget of $1.908 billion related to the completion
contract.”


After that settlement, states GT, costs “continued to increase
to $1.959 billion as of March 28, 2018…attributed to a variety of change orders…”
following which, on October 22, 2018 Nalcor “issued a stop work order to
Astaldi”.


For readers wondering where at least some of their money went,
overruns paid to Astaldi are reiterated below:

So many questions await both Nalcor and Nalcor that it is
possible to mention only a few others. 


For example, there is no reference in the Report to incentives
for higher productivity. Did the collective agreement limit their use? Did any
of the bidders bring forward an incentive based system which rewarded
productivity either on a shift or individual basis? 


Were productivity data used by management to design an
incentive based system which might have provided bonuses to direct labour and
to supervisors, too? Were penalties imposed on Astaldi when they failed to meet
production targets? 


EY, in its interim report on the Muskrat Falls project dated
April 8, 2016 (page 13/20) made the following observation concerning the lack of
performance based incentives:


5.8 The contract structure was
designed to realize possible savings in construction labour productivity and
also to protect Nalcor from any labour cost overruns that might be experienced
by the contractor. It was intended that this would be achieved by including in
the contract a maximum value for labour that Nalcor would have to pay to the
contractor. However, the payment mechanism is based on person-hours expended
rather than m3 of concrete poured. This mechanism did not capture the potential
for poor contract management of labour and the consequent decoupling of labour
paid for from work completed (measured by m3 of concrete poured). As at
December 2015, the proportion of contract value paid to the contractor is
significantly greater than the proportion of the concrete that has been placed.



EY is describing a contract seriously deficient having decoupled
issues of cost and management performance and responsibility. It is surprising
that the same observation is not recorded by GT. It would be useful to know if
the two accounting firms agree on this and similar problems with the Astaldi
contract.

Valard Contract
– CT0327 – The HVdc Transmission Line

The award of this work package to Valard included construction
of a 1,080km 350kV HVdc transmission line, the Right of Way (“ROW”)
clearing from Muskrat Falls to Soldier’s Pond together with tower construction
and stringing of 350 kV HVdc cable. 


The work package, notes GT, was originally four separate
packages (CT0327, CT0343, CT0345 and CT0346) but were combined later into one Contract
labelled CT0327. The decision to merge the contracts followed on the heels of
Nalcor’s decision not to accept a contracting strategy that split the project
into a large number of relatively small contracts, as reportedly employed by
Hydro Quebec. On this issue, GT reports that Nalcor took the advice of its bankers
rather than its Consultant, SNC Lavalin.


In the context of the whole Muskrat Falls Project, the “Construction
of HV dc Transmission Line was the second largest work package, accounting for
approximately $788 million (20%) of the total cost variance of $3.9 billion as of
March 2018”, according to the Forensic Auditor. Adjusted for “transfers from
other work packages and scope changes of $139 million the overrun on this work
package is $649 million”. 


GT attributes this figure to “a combination of factors
including contracts awarded in excess of budget, settlement agreement, and
change orders due to items such as geotechnical conditions different from
planned and the conductor proud strand issue (net of insurance proceeds) and
unallocated budget amounts.” (p.41)


At DG3, and Sanction, the Estimate for this work package
totalled $735 million including estimated escalation of $62 million. How did
the TL end up costing $1.523 billion? The Exhibit (below) offers a breakdown.
Puzzling, however, is the line item described as “transfers from other work
packages and scope changes”. While GT asked Nalcor for details, it states that
they were “unable to confirm the reason for $139 million of those increases.”

If Nalcor knew anything about construction, mega or otherwise,
it ought to have been found in transmission line construction. But even here
amateur hour is manifest with egregious financial consequences. 


GT explains that 40% of the engineering on the TL was
completed prior to calculation of the Base Estimate. But Nalcor had not
completed any geotechnical
examination along the proposed line, not even enough to establish baseline soil
conditions which might have helped the estimators. “We had to make assumptions
based on mapping…” stated the Deputy MF Project Director. In an interview with
BJ Ducey, Senior Vice President, Quanta Services (parent company of Valard
Construction) GT records him stating that: “… the actual conditions
proved out to be different than what was assumed…” Essentially, Valard used Nalcor’s
assumptions to enter into a negotiated agreement through what was termed “open
book negotiation” having dispensed with a competitive tender process. Due to
unexpectedly poor soil conditions, Valard states that “The assumed family of
foundations were not working… “Valard’s legal counsel confirmed
“That…part of the settlement…reached, is payment for these modified
foundations…” (p.47)


In addition, a “number of design changes were made to increase
the design reliability and robustness of the HV dc transmission line in the
period of 2013 – 2014″. Those design changes were a result of “Dark
NL”. Also coming out of Liberty’s review of reliability issues relating to
Muskrat was an acknowledgement “that NL Hydro’s operations and maintenance
philosophy needed adjustment, and that a near permanent access network would be
required…” (P.48)  Grant Thornton
attributes an additional cost of $212 million for this permanent access road or
Right of Way (ROW) including for geotechnical conditions, delays in permitting,
terrain and weather conditions. 


Notable, too, is that Nalcor succeeded in collecting only $25
million of the $58 million cost having accepted and strung kilometers of a
defective or “popped” cable described as “proud stranding”. Strangely, GT does
not comment on Nalcor’s Quality Control system that allowed the cable to be accepted
in the first place going through several stages of handling and stringing unnoticed.


At bottom, however, as GT states, “Nalcor accepted the risk of
geotechnical conditions being worse than what was anticipated in the base
estimate.”  


As noted, Nalcor did not pursue a “Bid” strategy with this
contract. Having reviewed the responses to an RFP, Nalcor concluded that only
Valard had the technical and financial qualifications to undertake any of the
originally constituted four work packages for the TL. Yet, at the
pre-qualification stage, Nalcor states that “We have significant interest in
firms to prequalify for CH0007 – at the end 4 bidders were pre-qualified – 3
are international/global firms”. (p.116) It is not clear why this “significant
interest” evaporated. GT offers no transparency on the issue.


Engineering,
Procurement, Contracting and Management (EPCM)

At the time of Project Sanction, the process of jettisoning SNC-Lavalin
as Nalcor’s EPCM contractor was already underway. Nalcor had decided to pursue an
“Integrated” management approach to the project. The strategy left SNC only with
responsibility for delivering the “E” or engineering design services while the
“PCM” portion of “EPCM” was brought in-house, at Nalcor. 


This is a very important issue and not just because, from the
earliest days, the public was unaware that Nalcor was having problems with its
EPCM contractor of a magnitude that, aside from the cost and schedule issues it
was facing, represented a sound basis for delay or cancellation of the project.
Determined to proceed, Nalcor substituted one “B-Team” for another. 


The decision to proceed with an “integrated” management
strategy was not announced until March, 2013. Seemingly, SNC-Lavalin had failed
to assign competent management to the project at the outset. Rather than look
elsewhere for an experienced engineering services contractor, Nalcor essentially
permitted the same inexperience that had managed the pre-Sanction activities to
also oversee the construction phase, a decision with foreseeable consequences. 


The Budget for EPCM services was re-allocated in January, 2014
but EPCM services combined at DG3 amounted to $712 million. By April 2018 the
budget for those services amounted to $1.12 billion reflecting, according to
GT, cost increases of $406 million.

It is not difficult to discern the knock-on effect of Nalcor’s
poor decision-making at the start, including the choice of Astaldi and the
decision to proceed with construction of the Transmission Line in the absence
of even basic geotechnical testing or data. Having removed SNC Lavalin what did
Nalcor do to ramp up quality assurance and control? How much of the $406
million went into quality control? GT does not tell us the answer to this
important question. This remains part of the unfinished business which GT must
perform before signing off on this forensic audit!


Other
Issues
:

Other issues covered by GT included the qualifications of the
project management team, Nalcor’s contracting strategy as well as the origins
and journey of the much-heralded SNC-Lavalin Risk Management Report, brought to
the public’s attention by CEO Stan Marshall. That’s the Report, according to some
insiders, that was accepted by Ed Martin with “clasped” hand.


This summary will not deal with those issues except in a
cursory way, in part for reasons of brevity but also because Grant Thornton’s
treatment of them is far more descriptive than analytical. We would like, for
example, to have seen more in-depth treatment of Nalcor’s decisions reflecting failures
of both processes and people, and their financial impacts. Key among them is
the decision to select Astaldi and why their delay in ramp-up, alone, didn’t
cause alarms to go off at Nalcor and instigate a replacement. 


Other questions that elude are these: was Astaldi solicited by
Nalcor or did the Company respond to an RFP? 
Did Nalcor’s RFP require a “lump-sum” bid? Did any contractor submit a
“lump-sum” bid? Were the people who assessed Astaldi’s bid competent to do so? Answers
to those questions would constitute just a beginning. 


GT also concluded “that the documented policies and procedures
governing Nalcor’s conduct in retaining and subsequently dealing with
contractors were in accordance with best practice.” The Forensic Audit
continues: “Generally, with the exception of Nalcor’s oversight of Astaldi’s
work (as described in section 4 of this report), their conduct in retaining and
subsequently dealing with contractors did not contribute to project cost
increases and project delays.” (P.70)


Frankly, this is a surprising observation. It is difficult to
understand how GT can come to such a conclusion when large expenditures are not
explained, including the $139 million for the LIL?


Indeed, the major award to Astaldi represents astoundingly
poor policies and procedures and is illustrative of the poor judgement which
Nalcor’s senior people brought to the project. However, a good many engineers
and contractors who worked at Muskrat Falls would not concur with GT’s far too
charitable appraisal of Nalcor’s management skills. On this account, the
Muskrat Falls Concerned Citizens Coalition might want to begin comparing Nalcor’s
safety record at Muskrat against, say, the Hebron construction project. 


We had expected more from GT in their appraisal of Nalcor’s
actions in managing the project. GT seems content to leave to the Commissioner,
through the process of examining Witnesses, to render an assessment of Nalcor’s
decisions and to ascribe responsibility for them. Nevertheless, some of GT’s other
observations are worth noting even if they contradict the rather soft GT finding
just referenced. GT states that:  


         
“The core project management team, with the
exception of Ron Power did not have any hydro experience….There were other
individuals on the integrated team that had significant hydro experience,
however these individuals had on average less than 16 years mega-project
experience.”
         
“Nalcor selected a procurement strategy to use
large packages, less interfaces and more risk transfer to contractors. This
decision was contrary to their research…and contrary to SNC’s opinion that the
construction packages should be smaller. …..Nalcor has indicated that
financiers preferred larger work packages“.
         
“Nalcor’s project risk management policies and
procedures were well defined and documented.” However, GT reports that “From
Sanction in 2012 to 2016, when project risks were materializing, there was no
formal QRA (Quantitative Risk Analysis) process completed.
         
“….while risk registers were maintained, the
overall final forecast cost and 
schedule did not reflect costs or schedule
changes until they were committed.”

         
“Nalcor…increase(d) the contingency several times
during the project for an approximate amount of $540 million.

         
Nalcor’s strategy to mitigate the risk of
“Availability and retention of skilled 
construction labour” was to develop a
construction schedule based upon “achievable 
labour productivity.” Yet, according to Nalcor’s
own risk advisor, there was a 
3% chance of Nalcor achieving that schedule.

         
On the issue of the SNC-Lavalin Risk Report, the
Forensic Audit concluded, among other things, V-P Gilbert Bennett and Project
Director, Paul Harrington (and possibly more people from Nalcor) knew the SNC
Risk Report existed and knew that the contents of the report pertained to LCP
project risks. Harrington made a decision not to ask for the report and
recommended to Mr. Bennett that SNC keep it as an internal document in draft
form and not provide it to Nalcor. Mr. Card of SNC remembered discussing the
SNC Risk Report with Ed Martin but the latter has no recollection of it.

This summary and appraisal of the second Forensic Report of
Grant Thornton only touches on the larger issues examined even if
insufficiently. Nevertheless, we are emboldened by the Report and intend to
direct our efforts to ensuring that the issues needing further illumination are
brought before the Commission.


Many of the issues raised are unsettling, especially the knowledge
that in place of any financial restitution, we can only hope to settle for the
truth without any meaningful financial accountability by the perpetrators of
this public policy disaster. And that “truth” won’t be arrived at easily. With
certainty, a key issue is the disclosure that Nalcor knew, prior to “Financial
Close”, that its paltry contingency funding was exhausted, that the project
would suffer significant overruns and delay, and still did not bother to inform
the public or reassess the implications of proceeding.


We would single out two other issues by way of conclusion. 

First, the independence of the Independent Engineer. This is a
matter addressed on many occasions by the Uncle Gnarley Blog. One of those
included information obtained under ATIPPA to the effect that Nalcor had edited
at least one and possibly more of the IE Reports to the Federal Government.  


In the current Report, GT also provided proof that Nalcor had
been given editorial discretion (p. 16) over at least one Report, resulting in
material changes (based upon a comparison of three drafts). Taken together,
such interference may have constituted a conflict of interest on the part of
Nalcor. Should the IE have refused such changes? What other changes were made
in other reports issued by the IE? Did GT review all of the Reports? Did the IE
properly inform the Government of Canada on a timely basis as to the
existential financial perils facing the project at the start and throughout the
construction phase? We believe that these are fundamental questions which
ultimately speak to the issue of Federal complicity in the sanctioning process.


The Coalition has written to the Board of Directors of Nalcor
concerning the editing of IE reports and we will be filing this correspondence
as an Inquiry Exhibit along with the response from the Board. The first phase
of the Inquiry is replete with examples where Nalcor and other public officials
protected their reputations by interfering with and editing reports from reports
which were intended to be independent of Nalcor and immune from their
manipulation and falsification!


Finally, there is the matter of SNC-Lavalin. The question
raised is this: why did Nalcor remove the Company from virtually every role
except engineering design, in spite of its actual world-class record in the
management of hydroelectric projects? 


Was there any evidence that the SNC Lavalin Risk Analysis was
prompted by concern over the Astaldi contract and the award of such a large
package to a single contractor? Would this explain the timing of the risk
analysis and Nalcor’s strangely defensive reaction in refusing to acknowledge
receipt of the SNC Lavalin report? 


An even larger concern is that Nalcor had acknowledged the
possibility of a $500 million overrun due to identified projects risks. The GT Report,
in contrast, (p. 135) confirms that Nalcor’s risk assessment was fundamentally
inadequate having failed to fully quantify the risks of the project. GT confirms
that “The calculated risk exposure from the SNC Risk Report exceeded Nalcor’s calculated
exposure by an approximate range of $600 million to $1.7 billion.” (p.136)


Did SNC Lavalin get in the way of Nalcor’s preferred narrative
that all was in “alignment” for project sanction? Were the legal troubles
hanging over SNC at that time opportunistic, allowing Nalcor to rid itself of a
party that might have known too much?


Taken together, is there evidence of malfeasance in the GT
Report? Is this an issue better assessed by others or should it be an integral
part of the forensic audit?


For our part, we believe that the public deserves answers to
the questions which the Forensic Audit raises, all of which are fundamental.
That is the very least a democratic society can grant to a citizenry mislead
and misinformed both by their government and Nalcor. 


The GT report is incomplete and this is no surprise because
the project is continuing, with many loose ends that may come apart. The
software problem with General Electric is one of the many unresolved issues.
The replacement of Astaldi is both unresolved and volatile. We believe it is
important that the Commissioner seek from GT a series of progress reports over
the coming months, no less frequently than quarterly. We expect that the Nalcor
CEO will provide an update when he appears as a witness in June. However the
Commissioner will need to have an up to date report from its forensic auditor
before submitting his final report at the end of the year. One of the great
unknowns which will be disclosed before the Commissioner becomes functus
officio is whether first power is achieved on schedule in November of 2019.


Muskrat
Falls Concerned Citizens Coalition

Ron Penney

David Vardy

Des Sullivan

 

Des Sullivan
Des Sullivan
St. John's, Newfoundland and Labrador, Canada Uncle Gnarley is hosted by Des Sullivan, of St. John's. He is a businessman engaged over three decades in real estate management and development companies and in retail. He is currently a Director of Dorset Investments Limited and Donovan Holdings Limited. During his early career he served as Executive Assistant to Premier's Frank D. Moores (1975-1979) and Brian Peckford (1979-1985). He also served as a Part-Time Board Member on the Canada-Newfoundland Labrador Offshore Petroleum Board (C-NLOPB). Uncle Gnarley appears on the masthead representing serious and unambiguous positions on NL politics and public policy. Uncle Gnarley is a fiscal conservative possessing distinctly liberal values and a non-partisan persusasion. Those values and opinions underlie this writer's views on NL's politics, economy and society. Uncle Gnarley publishes Monday mornings and more often when events warrant.

REMEMBERING BILL MARSHALL

Bill left public life shortly after the signing of the Atlantic Accord and became a member of the Court of Appeal until his retirement in 2003. During his time on the court he was involved in a number of successful appeals which overturned wrongful convictions, for which he was recognized by Innocence Canada. Bill had a special place in his heart for the underdog.

Churchill Falls Explainer (Coles Notes version)

If CFLCo is required to maximize its profit, then CFLCo should sell its electricity to the highest bidder(s) on the most advantageous terms available.

END OF THE UPPER CHURCHILL POWER CONTRACT: IMPROVING OUR BARGAINING POWER

This is the most important set of negotiations we have engaged in since the Atlantic Accord and Hibernia. Despite being a small jurisdiction we proved to be smart and nimble enough to negotiate good deals on both. They have stood the test of time and have resulted in billions of dollars in royalties and created an industry which represents over a quarter of our economy. Will we prove to be smart and nimble enough to do the same with the Upper Churchill?

41 COMMENTS

    • The RCMP ought to be investigating, but who would fund the investigation? They would need forensic audits of their own and a lot more forensic that the Grant Thornton audit. It would have to delve deep into SNC too. There are countless crooks here and shady deals everywhere. If we had a functional democracy that served the public we would be fining and or jailing current and former politicians, businessmen, well connected people and corporate executives. I predict that all the bad actors will get away with it and set the precedent for far worse in the future.

      I watched the Leah Remini's espose on Scientology. Regional investigations by the FBI get shut down by powerful people in DC. The IRS gave them tax exempt status. When many billions are involved, crooks are untouchable. It wouldn't surprise me of the NL RCMP would like to investigate but that Ottawa would shut it down.

      I would like to hear from an RCMP anon. Do you feel this would be a worthy investigation? What obstacles might get in the way? Is this too big to to handle or too political (provincial and federal)? Would pursuing it damage your career?

    • From the Globe and Mail:

      "A report this month by the Globe and Mail newspaper raised allegations the prime minister’s office pressured Trudeau’s former attorney general, Jody Wilson-Raybould, to settle fraud and corruption charges against construction company SNC-Lavalin Group Inc."

      So if Ottawa is protecting SNC Lavalin and perhaps tangled up in corruption, it seems unlikely they'd be encouraging the RCMP to look to hard at Muskrat Falls.

  1. Ha Ha power in Nov 2019! That is a good one!

    We have a weak GT report that does not probe the Nalcor dysfunction. Perfect for reporting to the judge with the rubber chicken, here come da judge!

    Nalcor and the faux board got their marching orders (along with the keys to the treasury) from their political masters. The fictions that followed were the result of the bungling from the oil boys.

    Who can break the veil of secrecy when no one can or will challenge the political origins of the MF farce that by now is costing well above 15 billion.

    • As things are commissioned, ugliness will surface. Software glitches, the need for spare parts, issues with the return DC path through the earth, insufficient water flows when it is held back due to upper Churchill operations, ongoing litigation with contractors, litigation over water rights, faulty towers, power electronics, turbine design, dam design defects that could have been picked up in peer review, mitigation costs … even the North Spur could break.

      Several years ago I heard 20 Billion and 2020. The 2020 part is coming true. I hope the 20B part doesn't but we are already 3/4 the way there.

  2. It looks like nobody gave a crap — full speed ahead. A few random things:

    The Valard sole source seems pretty crooked.

    "Due to unexpectedly poor soil conditions, Valard states that “The assumed family of foundations were not working… " — This reminds me of a guest speaker who came to MUN engineering several years ago (from Tulsa Oklahoma ?), who was an expert in difficult transmission lines, and told us that the conditions were amongst the most difficult on earth. How could conditions in Labrador or the Northern Peninsula be unexpectedly poor?

    If I saw a few close bids like $2.03 and $2.05 Billion from experienced bidders and two other bids that were half the price with questionable experience, that would be a huge red flag. That would be good grounds for excluding the low bids and re-evaluating if the project was affordable.

    Why all the contract secrecy? The redacted CH0032 for example. CH0032 Supply & Install Powerhouse & Spillway Hydro-Mechanical Equipment awarded 19-Dec-13 Andritz Hydro Canada Inc.

    I'd like to map all the contracts to NL business men and look for anomalies like conflict of interest.

    • If you google "Andritz" and "Sunny Corner" you will find several linked-in profiles such as this:

      "Site Manager at ANDRITZ HYDRO …. Worked as Superintendent for Sunny Corner"

      Cathy Bennett: a partner in New Brunswick based Sunny Corner Enterprises Inc. which also operates Northern Industrial Inc. in Labrador City. Brad Cabana had several blog entries on this. Does Sunny Corner subcontract to Andritz?

      Same Cathy Bennett that was minister of finance for awhile.

      All the swine are feeding at the public trough and they all seem to be intertwined with their business dealings.

    • "The Valard sole source seems pretty crooked.

      "Due to unexpectedly poor soil conditions, Valard states that “The assumed family of foundations were not working.."

      This is an old contractor trick in TLine construction, bitch about the soils.

      For Valard, it was shooting fish in a barrel.

    • The seemingly odd contractors that no experience in northern climate or other oddities like bidding half what experienced contractors did for a contract can probably be explained by their willingness to spray money in every direction that needed greasing a la SNC Lavalin.

      If only the judge had more than a rubber chicken or Learmonth could follow a corrupt lead the MF disaster might be unraveled and brought into focus.

  3. CH0031 was also redacted above … redactions bug me, so digging around I see ..

    The scope of work of Package CH0031 includes Mechanical piping, HVAC systems and Powerhouse, Intake, Dams and Spillway Auxiliary Electrical Systems and installation of Major Electrical Equipment and cabling under the supervision of Suppliers.

    Bidders were: Black & McDonald Limited (Mt Pearl) and Cahill-GanotecJoint Venture.

  4. The key question is why hide the estimates and is most often answered by financial gain. Follow the money. Who owns the head hunting companies that are making millions of mark-up for doing nothing. Who is really Astaldi's Canadian partner. Who owns all the numbered companies doing business on MF.

    It is time to get a subpoena for the legal right to find the owners.

    • This corrupt farce is at the point where everything should be blown wide open. Expose all contracts and beneficiaries including the ownership of all numbered companies that have Muskrat Falls related contracts. The public needs this to follow the money trail. I'd like backups of Nalcor's and GNL's e-mail system so that I could mine it for corruption and build a network of connections between various addresses. Free software exists to do this. An honest democratic government needs no secrets from those it is supposed to represent.

  5. it states that they were “unable to confirm the reason for $139 million of those increases.”

    What come to mind is corruption, skimming off the top, bribes, kickbacks, payoffs, dirty dealing, cork screwing and so on! Unexplained means hidden. Hidden means crooked and not above board.

  6. If the Inquiry has no mandate to lay or recommend charges for what has transpired, my question is does it have the authority to lay charges for " lying on the stand"? It is obvious that those who stand to lose the most will do anything to protect themselves which means avoiding, at all costs, any acceptance of complicity in any wrongdoing. e.g can you see EM and/or GB admitting guilt??

  7. Clearly the Board had a fiduciary responsible to abort the project, as early tender numbers blew the budget allocation into the next century. This fraud on the shareholder. Will the shareholder now bring a class action against these "fine upstanding people".

  8. There has to be a money trail here. What has happened (that we know of so far) is mind-boggling in what appears to be high corruption and wilful negligence which has resulted in the purging the public purse and the future of generations to come. What possible reason would there be to do this if it were not a "hands in the til" situation.
    DISGRACEFUL.

    • So consider your own appointment to the shadow Board of NALCOR. The Project Manager lays out the bids on the Italian company with several doubts about the Low bid, quality, financial capability, Safety, etc. The Bid ,if selected, will blow the Budget out of sight. What would you say in behalf of the shareholder, from whom you receive prestigious, and prodigious compensation? Where is your loyalty?

    • At Transportation and Works, low bids from questionable bidders are considered a red flag, especially if experienced bidders come up with very similar but higher figures. You can disqualify low bids.

      When MUN tendered the science building, it was too expensive so they went back to the drawing board. You don't tender work you cannot pay for.

      I can't think of anywhere else where this kind and magnitude of corruption would even be possible. These aren't small overruns — we are talking about many billions. Overruns big enough to build Trump's wall with Mexico.

      At a minimum I demand PEGNL revoke the P.Eng. from any engineers involved with enabling fraud. CPANL should go after any chartered accountant that feel $139,000,000 unexplained is not a problem. Professional members shouldn't have to file complaints against their colleagues and risk their careers. The professional organizations should be following this monumental hearing and rise to the occasion. It is too bad that in the case of PEGNL, it has been infested with Nalcor executives.

      All of our institutions are rotten.

  9. Did SNC bribe the Newfoundland Liberals via directed campaign contributions to keep Muskrat Falls alive?

    https://www.cbc.ca/news/politics/election-financing-snclavalin-charbonneau-1.4984823

    The CBC comments are worth reading — looks like the public is disgusted by federal government coverups and corruption.

    A SNC official pleaded guilty and gets a $2000 fine — so now the public can't see the charges or who find out who was illegally funded. What a crooked system.

    "Employees were encouraged to donate to federal political parties, then were reimbursed by the company through "false refunds for personal expenses or payment of fictitious bonuses."

    Given that SNC is known for bribery, and is blacklisted by the world bank for corruption, I can only assume that they would have thrown money at the Newfoundland Liberals to protect their contracts and discourage Ball from killing the project. What is the chance that there was a real business reason for SNC to purchase Danny Williams company other than purchasing influence (bribery).

    Semi related: Given that the World Bank has a blacklist of corrupt business, why do we do business with them in this province? Here is the blacklist. Filter by Canada. There are some with Newfoundland office addresses!

    • They don't care. Just as our local sociopaths don't care if they add 12B to the provincial debt, federal sociopaths don't care if they add billions or trillions to the national debt. It isn't their personal money and they benefit from it in some manner. Banks of course, love it.

  10. Anyone listening to the Inquiry today?

    I'm impressed that the Commissioner stepped in a few minutes ago and shut down Ed Martin's lawyer who was trying to suggest that going over budget was okay because the CPW analysis showed Muskrat was better by 2.4 billion therefore spending their way into this CPW difference amount was okay.

    What this seems to show is that Ed Martin regarded the 2.4B as his management reserve fund he felt authorized to use. As the Commissioner explained, 6.2B was the only approved amount and no more.

    This parlay uncovers another dimension of Ed Martin's arrogance. Oh, what a slimeball he is.

  11. Have not been able to comment in the past couple of weeks as I think someone is again lobing scud missiles at my old computer technology, so trying a public place today. The blog thinks I am a robot also and won't allow me to post. Oh well lots of other things to read without my one cent worth. Will kept it brief , but noticed the government officials and politicians that are well lawyered up were quick to jump to their feet and proclaim that GT had not said that Eddie had told any of them that the budget was blown before they got started, they just didn't know, so are totally innocent of any over runs. Yes Frankenstein made no contact with them and operated independently of them for a couple of years, not even calling to say I need more money, or phone home. So takes a couple of premieres and ministers right in the clear. Namely Marshall and Davis. Like Judes have washed their hands completely from the boondoggle. The call only came when Eddie ran out of money, so he called home and Ball et al answered. Send money or I quit was the first words uttered. I am still 2.4$ B below the island option, and holding SNC to ransom to boot so tell Justin to anti up pronto. And no balking. Ball Balked which was the beginning of another phase of the boondoggle as the monster made a 180 degree turn and headed for warmer climates. My say for the day says joe blow.